Name of the Project एकात्मिक नाला बांधणी
Implementing Agency Thane Municipal Corporation, Thane, Maharashtra.
Before:
After:
History:
Integrated Nalla development Project is implemented under Jawaharlal Nehru National Urban Renewal Mission. (JNNURM) Under Integrated Nalla development Project Phase I, Phase II & Phase III major nallas are constructed.
Sr. No. Phase Area covered by SWD prior to JNNURM(Sq. Km) Area covered by SWD post JNNURM(Sq. Km)
1 INDP Phase-I 22.17 29.56
2 INDP Phase-II 3.72 24.87
2 INDP Phase-III 0.00 26.06
Outcome:
  • Encroachments in Nalla are removed.
  • Obstructions due to various utility services in the flow of water are removed.
  • Due to systematic disposal of storm water from catchments to creek, water logging & flooding situations in last year is reduced. i.e. before project there were 89 water logging spots which are now reduced to 12.
  • Annual maintenance for repairing Nalla walls is reduced & hence O & M expenditure is minimized.
  • As flooding in the city area is reduced, cost for maintenance of asphalt road is decreased.
  • Health & properties of the citizens are protected as water logging & flooding is decreased.
ठाणे महानगरपालिके विषयी
कार्यालयीन कामकाज
ठाणे शहरातील सुविधा
ठाण्यातील करमणुक
ETender
Town Planning Department
LBT

© 2019 टीएमसी. सर्व हक्क राखीव.
\
\
Designed & Powered by TMC IT Department